United States › Grid › Interconnection queues › Louisiana
BATTERY STORAGE · MISOBattery storage project J1602, Ouachita Parish County
Battery storage project J1602, Ouachita Parish County is a 25.0 MW battery storage request with a signed interconnection agreement in the MISO interconnection queue, in Ouachita Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusConsented
- PlanningQueued Nov 2021 (completed)
- ConsentedJan 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1602
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Rilla 115kV substation (Same as J1239)
- Location
- Ouachita Parish County, Louisiana
- Technology
- Battery: 25.0 MW
- Total requested
- 25.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 2 November 2021
- Agreement signed
- 18 January 2023
- Proposed online date
- October 2024
Location
Marker shows the centre of Ouachita Parish County; the queue data does not give exact sites.
Other requests in Ouachita Parish County
- Solar project J1239, Ouachita Parish CountySolar · 100 MW · under construction
- Solar project J2708, Ouachita Parish CountySolar · 500 MW · in study
- Solar project J2704, Ouachita Parish CountySolar · 500 MW · in study
- Solar project J2317, Ouachita Parish CountySolar · 225 MW · in study
- Solar project J2816, Ouachita Parish CountySolar · 100 MW · in study
- Battery storage project J4140, Ouachita Parish CountyBattery storage · 100 MW · in study
- Solar project J2917, Ouachita Parish CountySolar · 80.0 MW · in study
- Solar project J4049, Ouachita Parish CountySolar · 75.0 MW · in study
- Replacing 49 MW of gas generation with BESS; SterlingtonOther · 49.0 MW · in study
- Gas project J4022, Ouachita Parish CountyGas · 1,509 MW · withdrawn
- Solar project J852, Ouachita Parish CountySolar · 100 MW · withdrawn
- Solar project J1883, Ouachita Parish CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem