🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 165

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 165 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project Q66, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Redbud-Gaylord 34.5 kV
Solar
30.0 MWPaused / redesign Frederick, VAPJM Jul 2020target 2026
Gas project Q81, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Jun 2021target 2025
Battery storage project G0733, Benton County
Battery storage
30.0 MWIn study Benton, WAWest Mar 2022target 2025
Solar project GI-2010-4, Alamosa County
Solar
30.0 MWAgreement signed Alamosa, COWest Feb 2010target 2012
Battery storage project AI2-311, Washington County
Battery storage
30.0 MWIn study Washington, MDPJM Mar 2023target 2025
Spinel Solar
Solar
30.0 MWPaused / redesign Medina, TXERCOT Aug 2017
Black Diamond Solar
Battery storage · Black Diamond Solar Power, LLC
30.0 MWIn study Christian, ILPJM Sep 2020target 2022
Solar project 957086, Darlington County
Solar
30.0 MWIn study Darlington, SCSoutheast Jun 2024
Solar project 337, Lake County
Solar
30.0 MWAgreement signed Lake, TNSoutheast Jan 2018target 2020
Solar + storage project 783, Natrona County
Solar + storage · Dinosolar, LLC
30.0 MWAgreement signed Natrona, WYWest Aug 2016target 2024
Battery storage project AI2-227, Amherst County
Battery storage
30.0 MWIn study Amherst, VAPJM Mar 2023target 2023
Gas project 12-048, Morrow County
Gas
30.0 MWPaused / redesign Morrow, ORWest Feb 2012target 2012
Enchanted Rock NEWPP
Gas · Generate ER-NG, LLC
30.0 MWAgreement signed Harris, TXERCOT Nov 2021target 2026
Solar + storage project AH2-411
Solar + storage
30.0 MWIn study KYPJM Mar 2022target 2025
Coal project 978035, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
South Orchard
Battery storage
30.0 MWAgreement signed Cumberland, NJPJM Sep 2019target 2028
Battery storage project AH2-059, Prince William County
Battery storage
30.0 MWIn study Prince William, VAPJM Dec 2021target 2027
Coal project 978034, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Glen Falls Facility
Gas
30.0 MWAgreement signed Harrison, WVPJM Sep 2016target 2029
Surplus; J903
Other
30.0 MWIn study MISO Oct 2020
Gas project Q65, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023
Other project PP00054, Darlington County
Other
30.0 MWIn study Darlington, SCSoutheast Oct 2025target 2027
Solar project AH2-117, Pike County
Solar
30.0 MWIn study Pike, KYPJM Feb 2022target 2026
Onshore wind project J1470, Benton County
Onshore wind
30.0 MWAgreement signed Benton, INMISO Apr 20192020
Solar project AG2-081, Montgomery County
Solar · SR Fayette II, LLC
30.0 MWIn study Montgomery, KYPJM Mar 2025target 2024
Solar project J2908, Morgan County
Solar
30.0 MWIn study Morgan, ILMISO Jul 20222023
Battery storage project AH2-058, Prince William County
Battery storage
30.0 MWIn study Prince William, VAPJM Dec 2021target 2026
Onshore wind project PIS052, Carbon County
Onshore wind · PacifiCorp
30.0 MWIn study Carbon, WYWest Feb 2024target 2024
Battery storage project J466, Huron County
Battery storage
30.0 MWAgreement signed Huron, MIMISO May 2015target 2015
Battery storage project AG2-566, Prince Edward County
Battery storage · Gabriel Storage, LLC
30.0 MWIn study Prince Edward, VAPJM Feb 2025target 2024
Solar project AH2-057, Buckingham County
Solar
29.9 MWIn study Buckingham, VAPJM Dec 2021target 2025
Hoffman Falls Wind 2
Onshore wind · Liberty Renewables Inc.
29.8 MWIn study Madison, NYNYISO Aug 2024target 2027
Solar project 287, Fairfield County
Solar
29.7 MWIn study Fairfield, SCSoutheast May 2025target 2027
Solar project AI2-471, Montour County
Solar
29.5 MWIn study Montour, PAPJM Mar 2023target 2025
Solar project AI2-338, Charles City County
Solar
29.2 MWIn study Charles City, VAPJM Mar 2023target 2024
Battery storage project AH2-075, City Of Hampton County
Battery storage
29.1 MWIn study City Of Hampton, VAPJM Jan 2022target 2024
Solar project AI2-473, Montour County
Solar
29.0 MWIn study Montour, PAPJM Mar 2023target 2026
Gas project G005, Lincoln County
Gas
29.0 MWIn study Lincoln, MNMISO Feb 1999target 2004
Geothermal project Company LR, Lander County
Geothermal
29.0 MWAgreement signed Lander, NVWest Sep 2021target 2024
Geothermal project IA-PNM-2015-01, Doña Ana Cty County
Geothermal · ORNI 24
29.0 MWAgreement signed Doña Ana Cty, NMWest Jul 2015target 2021
Gas project GEN-2020-061, Cass County
Gas
29.0 MWAgreement signed Cass, MOSPP Apr 2020target 2026
Geothermal project IA-PNM-2014-04, Dona Ana Cty County
Geothermal
29.0 MWIn study Dona Ana Cty, NMWest Mar 2014target 2018
Solar project AI1-119, Kendall County
Solar
28.8 MWIn study Kendall, ILPJM Sep 2022target 2026
Solar project AI2-152, Madison County
Solar
28.8 MWIn study Madison, INPJM Mar 2023target 2025
Solar project AI2-410, Dekalb County
Solar
28.5 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project 572354, Cherokee County
Solar
28.3 MWAgreement signed Cherokee, SCSoutheast Jun 2022target 2027
Solar project AH2-379, Worcester County
Solar
28.3 MWIn study Worcester, MDPJM Mar 2022target 2026
Coal project GI-43, Randolph County
Coal
28.2 MWIn study Randolph, MOSoutheast Nov 2009target 2012
Page 165 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)