United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTSpinel Solar
Spinel Solar is a 30.0 MW solar request suspended in the ERCOT interconnection queue, in Medina County, Texas.
Queue statusPaused / redesign
- PlanningQueued Aug 2017 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 20INR0025
- Grid region
- ERCOT (Texas)
- Location
- Medina County, Texas
- Technology
- Solar: 30.0 MW
- Total requested
- 30.0 MW
- Queue status
- Suspended
- Entered queue
- 9 August 2017
Location
Marker shows the centre of Medina County; the queue data does not give exact sites.
Other requests in Medina County
- Devine Mary BESSBattery storage Β· 201 MW Β· in study
- Chacon CreekBattery storage Β· 189 MW Β· in study
- Ranger BESSBattery storage Β· 155 MW Β· in study
- Dunlay SolarSolar Β· 151 MW Β· in study
- Hondo Arroyo StorageSolar + storage Β· 101 MW Β· in study
- Adam Bryant BESSBattery storage Β· 99.5 MW Β· in study
- Hondo Arroyo SolarSolar + storage Β· 60.4 MW Β· in study
- Cowboy SolarSolar Β· 208 MW Β· withdrawn
- Clarion SolarSolar Β· 180 MW Β· withdrawn
- Hedgehog SolarSolar Β· 85.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem