United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTCowboy Solar
Cowboy Solar is a 208 MW solar request withdrawn in the ERCOT interconnection queue, in Medina County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2019 (completed)
- Withdrawn / abandonedJul 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0461
- Grid region
- ERCOT (Texas)
- Developer
- AP Solar 1 LLC
- Connection point (POI)
- 8241 Razorback 138kV
- Location
- Medina County, Texas
- Technology
- Solar: 208 MW
- Total requested
- 208 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 12 November 2019
- Proposed online date
- December 2021
- Withdrawn
- July 2020
Location
Marker shows the centre of Medina County; the queue data does not give exact sites.
Other requests in Medina County
- Devine Mary BESSBattery storage Β· 201 MW Β· in study
- Chacon CreekBattery storage Β· 189 MW Β· in study
- Ranger BESSBattery storage Β· 155 MW Β· in study
- Dunlay SolarSolar Β· 151 MW Β· in study
- Hondo Arroyo StorageSolar + storage Β· 101 MW Β· in study
- Adam Bryant BESSBattery storage Β· 99.5 MW Β· in study
- Hondo Arroyo SolarSolar + storage Β· 60.4 MW Β· in study
- Spinel SolarSolar Β· 30.0 MW Β· suspended
- Clarion SolarSolar Β· 180 MW Β· withdrawn
- Hedgehog SolarSolar Β· 85.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem