United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Cowboy Solar

Cowboy Solar is a 208 MW solar request withdrawn in the ERCOT interconnection queue, in Medina County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2019 (completed)
  2. Withdrawn / abandonedJul 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0461
Grid region
ERCOT (Texas)
Developer
AP Solar 1 LLC
Connection point (POI)
8241 Razorback 138kV
Location
Medina County, Texas
Technology
Solar: 208 MW
Total requested
208 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
12 November 2019
Proposed online date
December 2021
Withdrawn
July 2020

Location

Marker shows the centre of Medina County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Medina County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem