United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTClarion Solar
Clarion Solar is a 180 MW solar request withdrawn in the ERCOT interconnection queue, in Medina County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2021 (completed)
- Withdrawn / abandonedApr 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0025
- Grid region
- ERCOT (Texas)
- Developer
- IBV Energy Partners LLC
- Connection point (POI)
- 5290 Lytle 138kV
- Location
- Medina County, Texas
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 28 February 2021
- Proposed online date
- August 2024
- Withdrawn
- April 2024
Location
Marker shows the centre of Medina County; the queue data does not give exact sites.
Other requests in Medina County
- Devine Mary BESSBattery storage Β· 201 MW Β· in study
- Chacon CreekBattery storage Β· 189 MW Β· in study
- Ranger BESSBattery storage Β· 155 MW Β· in study
- Dunlay SolarSolar Β· 151 MW Β· in study
- Hondo Arroyo StorageSolar + storage Β· 101 MW Β· in study
- Adam Bryant BESSBattery storage Β· 99.5 MW Β· in study
- Hondo Arroyo SolarSolar + storage Β· 60.4 MW Β· in study
- Spinel SolarSolar Β· 30.0 MW Β· suspended
- Cowboy SolarSolar Β· 208 MW Β· withdrawn
- Hedgehog SolarSolar Β· 85.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem