🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Hondo Arroyo Storage

Hondo Arroyo Storage is a 101 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Medina County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0437
Grid region
ERCOT (Texas)
Developer
Hondo Creek Solar, LLC
Connection point (POI)
Tap 138 kV 5225 Hondo - 5813 Pearson
Location
Medina County, Texas
Technology
Battery: 101 MW · Battery
Total requested
101 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 December 2024
Proposed online date
July 2028

Location

Marker shows the centre of Medina County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Medina County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem