Coal project GI-43, Randolph County

Coal project GI-43, Randolph County is a 28.2 MW coal request in interconnection study in the Southeast interconnection queue, in Randolph County, Missouri, connecting to Associated Electric Cooperative, Incorporated.

Queue statusIn planning
  1. PlanningQueued Nov 2009 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2012 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-43
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Associated Electric Cooperative, Incorporated
Connection point (POI)
TH Switchyard (345 kV Bus)
Location
Randolph County, Missouri
Technology
Coal: 28.2 MW
Total requested
28.2 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
4 November 2009
Proposed online date
May 2012

Location

Marker shows the centre of Randolph County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Randolph County