United States › Grid › Interconnection queues › Virginia
SOLAR · PJMSolar project AI2-338, Charles City County
Solar project AI2-338, Charles City County is a 29.2 MW solar request in interconnection study in the PJM interconnection queue, in Charles City County, Virginia, connecting to Dominion.
Queue statusIn planning
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-338
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Providence Forge-Turner 115kV
- Location
- Charles City County, Virginia
- Technology
- Solar: 29.2 MW
- Total requested
- 29.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 2 March 2023
- Proposed online date
- September 2024
Location
Marker shows the centre of Charles City County; the queue data does not give exact sites.
Other requests in Charles City County
- Chickahominy Solar 1 and 2Solar · 320 MW · agreement signed
- Battery storage project AI1-013, Charles City CountyBattery storage · 200 MW · in study
- Chickahominy PowerGas · 1,600 MW · withdrawn
- C4GTGas · 1,060 MW · withdrawn
- Battery storage project AG2-475, Charles City CountyBattery storage · 500 MW · withdrawn
- Solar + storage project AG1-543, Charles City CountySolar + storage · 325 MW · withdrawn
- Solar + storage project AG2-070, Charles City CountySolar + storage · 325 MW · withdrawn
- Solar project AF1-329, Charles City CountySolar · 250 MW · withdrawn
- Gas project AF2-053, Charles City CountyGas · 200 MW · withdrawn
- Stony Run Solar Project, LLCSolar · 154 MW · withdrawn
- Battery storage project AH1-288, Charles City CountyBattery storage · 43.2 MW · withdrawn
- Battery storage project AG2-639, Charles City CountyBattery storage · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem