United States βΊ Grid βΊ Interconnection queues βΊ Virginia
BATTERY STORAGE Β· PJMBattery storage project AG2-639, Charles City County
Battery storage project AG2-639, Charles City County is a 20.0 MW battery storage request withdrawn in the PJM interconnection queue, in Charles City County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-639
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Developer
- ACE Development Company II, LLC
- Connection point (POI)
- Chickahominy 230 kV
- Location
- Charles City County, Virginia
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- April 2025
- Withdrawn
- July 2025
Location
Marker shows the centre of Charles City County; the queue data does not give exact sites.
Other requests in Charles City County
- Chickahominy Solar 1 and 2Solar Β· 320 MW Β· agreement signed
- Battery storage project AI1-013, Charles City CountyBattery storage Β· 200 MW Β· in study
- Solar project AI2-338, Charles City CountySolar Β· 29.2 MW Β· in study
- Chickahominy PowerGas Β· 1,600 MW Β· withdrawn
- C4GTGas Β· 1,060 MW Β· withdrawn
- Battery storage project AG2-475, Charles City CountyBattery storage Β· 500 MW Β· withdrawn
- Solar + storage project AG1-543, Charles City CountySolar + storage Β· 325 MW Β· withdrawn
- Solar + storage project AG2-070, Charles City CountySolar + storage Β· 325 MW Β· withdrawn
- Solar project AF1-329, Charles City CountySolar Β· 250 MW Β· withdrawn
- Gas project AF2-053, Charles City CountyGas Β· 200 MW Β· withdrawn
- Stony Run Solar Project, LLCSolar Β· 154 MW Β· withdrawn
- Battery storage project AH1-288, Charles City CountyBattery storage Β· 43.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem