United States βΊ Grid βΊ Interconnection queues βΊ Virginia
GAS Β· PJMChickahominy Power
Chickahominy Power is a 1,600 MW gas request withdrawn in the PJM interconnection queue, in Charles City County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2016 (completed)
- Withdrawn / abandonedFeb 2022 (project stopped here)
- ConsentedSep 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC1-107
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Chickahominy 500kV
- Location
- Charles City County, Virginia
- Technology
- Gas: 1,600 MW
- Total requested
- 1,600 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 26 October 2016
- Agreement signed
- 20 September 2019
- Proposed online date
- March 2024
- Withdrawn
- February 2022
Location
Marker shows the centre of Charles City County; the queue data does not give exact sites.
Other requests in Charles City County
- Chickahominy Solar 1 and 2Solar Β· 320 MW Β· agreement signed
- Battery storage project AI1-013, Charles City CountyBattery storage Β· 200 MW Β· in study
- Solar project AI2-338, Charles City CountySolar Β· 29.2 MW Β· in study
- C4GTGas Β· 1,060 MW Β· withdrawn
- Battery storage project AG2-475, Charles City CountyBattery storage Β· 500 MW Β· withdrawn
- Solar + storage project AG1-543, Charles City CountySolar + storage Β· 325 MW Β· withdrawn
- Solar + storage project AG2-070, Charles City CountySolar + storage Β· 325 MW Β· withdrawn
- Solar project AF1-329, Charles City CountySolar Β· 250 MW Β· withdrawn
- Gas project AF2-053, Charles City CountyGas Β· 200 MW Β· withdrawn
- Stony Run Solar Project, LLCSolar Β· 154 MW Β· withdrawn
- Battery storage project AH1-288, Charles City CountyBattery storage Β· 43.2 MW Β· withdrawn
- Battery storage project AG2-639, Charles City CountyBattery storage Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem