Gas project GI-116, New Madrid County

Gas project GI-116, New Madrid County is a 26.0 MW gas request with a signed interconnection agreement in the Southeast interconnection queue, in New Madrid County, Missouri, connecting to Associated Electric Cooperative, Incorporated.

Queue statusConsented
  1. PlanningQueued May 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-116
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Associated Electric Cooperative, Incorporated
Connection point (POI)
St Francis 161 kV
Location
New Madrid County, Missouri
Technology
Gas: 26.0 MW
Total requested
26.0 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
3 May 2023
Proposed online date
October 2024

Location

Marker shows the centre of New Madrid County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in New Madrid County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem