🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Missouri

SOLAR · MISO

Solar project J944, New Madrid County

Solar project J944, New Madrid County is a 200 MW solar request built and operating in the MISO interconnection queue, in New Madrid County, Missouri, connecting to Entergy.

Queue statusOperating
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedDec 2019 (completed)
  3. Construction (completed)
  4. OperatingOct 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J944
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Portageville - New Madrid 161kV Line
Location
New Madrid County, Missouri
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
16 June 2017
Agreement signed
17 December 2019
Proposed online date
October 2022
Came online
October 2022

Location

Marker shows the centre of New Madrid County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in New Madrid County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem