Other project GI-2021-144, Imperial County

Other project GI-2021-144, Imperial County is a 28.0 MW other request in interconnection study in the West interconnection queue, in Imperial County, California, connecting to Imperial Irrigation District.

Queue statusIn planning
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-2021-144
Grid region
West (non-ISO utilities)
Utility / transmission owner
Imperial Irrigation District
Connection point (POI)
92kV J line
Location
Imperial County, California
Technology
Other: 28.0 MW
Total requested
28.0 MW
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
8 March 2021
Proposed online date
December 2028

Location

Marker shows the centre of Imperial County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Imperial County