Interconnection queue in the USA — page 150

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 150 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AG2-384, Chesterfield County
Battery storage · Virginia Electric and Power Company
60.8 MWIn study Chesterfield, VAPJM Feb 2025target 2025
Battery storage project S0029, Crook County
Battery storage
60.8 MWIn study Crook, ORWest Feb 2024target 2026
Fallstone Solar SLF
Solar + storage · Fallstone Solar, LLC
60.6 MWIn study Falls, TXERCOT Dec 2024target 2028
Battery storage project AI2-307, Cecil County
Battery storage
60.5 MWIn study Cecil, MDPJM Mar 2023target 2026
Hondo Arroyo Solar
Solar + storage · Hondo Creek Solar, LLC
60.4 MWIn study Medina, TXERCOT Jun 2024target 2028
Bird Dog Energy Storage
Battery storage · VESI 37 LLC
60.4 MWAgreement signed Live Oak, TXERCOT Feb 2021target 2026
Borden Dino BESS
Solar + storage · Borden Dino Solar, LLC
60.3 MWIn study Borden, TXERCOT Apr 2025target 2028
Oriana BESS
Solar + storage · Oriana Solar LLC
60.3 MWAgreement signed Victoria, TXERCOT Aug 2021target 2028
Tipperary Solar
Solar · Tippsol
60.2 MWIn study Schleicher, TXERCOT Jun 2024target 2028
Stonewall Solar
Solar + storage · Stonewall PV, LLC
60.2 MWIn study Stonewall, TXERCOT May 2024target 2029
Lampe Solar
Solar · Gransolar Texas Seven LLC
60.2 MWIn study Washington, TXERCOT Aug 2021target 2027
Surplus; J878
Other
60.0 MWIn study MISO Apr 20212024
Solar project J1889, Linn County
Solar
60.0 MWIn study Linn, IAMISO Aug 2021target 2025
Moon Corner Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
60.0 MWIn study Richmond, VAPJM Sep 2020target 2031
Gas project 419, Martin County
Gas · FPL
60.0 MWIn study Martin, FLSoutheast Sep 2020target 2026
Solar project AG2-171, Lunenburg County
Solar · Couch Creek Solar LLC
60.0 MWIn study Lunenburg, VAPJM Feb 2025target 2024
Battery storage project J1863, Otsego County
Battery storage
60.0 MWIn study Otsego, MIMISO Aug 2021target 2024
Battery storage project J1880, Ottawa County
Battery storage
60.0 MWIn study Ottawa, MIMISO Aug 2021target 2024
Battery storage project J2376, Shelby County
Battery storage
60.0 MWIn study Shelby, ILMISO Sep 2022target 2024
Indigo Storage 4
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Oct 2023target 2026
Mt Olive Creek Solar
Solar
60.0 MWAgreement signed Russell, KYPJM Jun 2019target 2026
Mark Center Solar Project
Solar
60.0 MWAgreement signed Defiance, OHPJM Mar 2019target 2026
Solar project 286, Orangeburg County
Solar
60.0 MWIn study Orangeburg, SCSoutheast May 2025target 2027
Solar project 566580, Lee County
Solar
60.0 MWUnder construction Lee, SCSoutheast Jun 2022target 2028
Columbia County 1
Solar · Hecate Energy Columbia County 1, LLC
60.0 MWIn study Columbia, NYNYISO Jul 2017target 2027
Solar project AI1-105, Luzerne County
Solar
60.0 MWIn study Luzerne, PAPJM Aug 2022target 2026
Cayuga Solar
Solar · Cayuga Lake Solar, LLC
60.0 MWIn study Tompkins, NYNYISO Sep 2024target 2028
Edwards Calverton Battery Storage
Battery storage · Edwards Calverton Battery Storage
60.0 MWIn study Suffolk, NYNYISO Sep 2021target 2026
Gas project 657, Muhlenberg County
Gas
60.0 MWIn study Muhlenberg, KYSoutheast Oct 2024target 2030
Cricket Solar
Solar
60.0 MWAgreement signed Culpeper, VAPJM Oct 2016target 2029
Onshore wind project GI-2014-4, Logan County
Onshore wind
60.0 MWAgreement signed Logan, COWest Apr 2014target 2013
Solar + storage project 59, Adams County
Solar + storage
60.0 MWAgreement signed Adams, WAWest May 2018
Indigo Storage 2
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Sep 2023target 2026
Angela
Solar + storage
60.0 MWAgreement signed Tulare, CACAISO Apr 2018target 2025
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
Battery storage project AH2-032, Prince William County
Battery storage
60.0 MWIn study Prince William, VAPJM Nov 2021target 2026
Solar project BHCT G19, Pueblo County
Solar
60.0 MWIn study Pueblo, COWest Apr 2015target 2019
Agate Solar
Solar
60.0 MWPaused / redesign Ellis, TXERCOT Aug 2017
Taylor Creek Two
Solar
60.0 MWIn study Orange, FLSoutheast Feb 2024target 2026
Albemarle Beach Solar
Solar
60.0 MWAgreement signed Washington, NCPJM Jan 2019target 2026
Solar + storage project Q534, Navajo County
Solar + storage
60.0 MWIn study Navajo, AZWest Apr 2023target 2026
Sweetleaf Solar
Solar
60.0 MWPaused / redesign Halifax, NCPJM Aug 2017target 2027
Battery storage project G0708, Morrow County
Battery storage
60.0 MWIn study Morrow, ORWest Oct 2021target 2023
Horseshoe Bend Solar
Solar
60.0 MWAgreement signed Green, KYPJM Jul 2019target 2026
Indigo Storage
Solar + storage · Innovative Solar 245, LLC
60.0 MWIn study Fisher, TXERCOT Dec 2022target 2026
Battery storage project G0707, Morrow County
Battery storage
60.0 MWIn study Morrow, ORWest Oct 2021target 2023
Solar project J1649, Mccracken County
Solar
60.0 MWIn study Mccracken, KYMISO Mar 2021target 2025
Kce NY 21
Battery storage · KCE NY 21, LLC
60.0 MWIn study Suffolk, NYNYISO Aug 2024target 2029
Hydro project J1213, Iron County
Hydro
60.0 MWAgreement signed Iron, MOMISO Apr 2019target 2024
Nuclear project 25-IC-1301, Appling County
Nuclear
60.0 MWIn study Appling, GASoutheast Mar 2025target 2030
Page 150 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)