Surplus; J1067

Surplus; J1067 is a 60.0 MW other request in interconnection study in the MISO interconnection queue, in White County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusIn planning
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingMay 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1028
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
Reynolds - Burr Oak 345kV Line
Location
White County, Indiana
Technology
Other: 60.0 MW · Battery
Total requested
60.0 MW
Queue status
Active
Entered queue
31 May 2022
Came online
May 2024

Location

Marker shows the centre of White County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in White County