United States › Grid › Interconnection queues › Kentucky

SOLAR · MISO

Solar project J1649, Mccracken County

Solar project J1649, Mccracken County is a 60.0 MW solar request in interconnection study in the MISO interconnection queue, in Mccracken County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.

Queue statusIn planning
  1. PlanningQueued Mar 2021 (current stage)
  2. ConsentedJun 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1649
Grid region
MISO (Midcontinent)
Utility / transmission owner
BIG RIVERS ELECTRIC CORPORATION
Connection point (POI)
Shell - McCracken County 69.0kV
Location
Mccracken County, Kentucky
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
10 March 2021
Agreement signed
3 June 2025
Proposed online date
October 2025

Location

Marker shows the centre of Mccracken County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Mccracken County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem