United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

SOLAR Β· MISO

Solar project J2547, Mccracken County

Solar project J2547, Mccracken County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Mccracken County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2547
Grid region
MISO (Midcontinent)
Utility / transmission owner
BIG RIVERS ELECTRIC CORPORATION
Connection point (POI)
Bryan Road - McCracken County 161.0kV
Location
Mccracken County, Kentucky
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
July 2027
Withdrawn
October 2025

Location

Marker shows the centre of Mccracken County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Mccracken County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem