SOLAR · SOUTHEAST

Solar project LGE-GIS-2021-007, Mccracken County

Solar project LGE-GIS-2021-007, Mccracken County is a 120 MW solar request suspended in the Southeast interconnection queue, in Mccracken County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
LGE-GIS-2021-007
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Louisville Gas & Electric and Kentucky Utilities Energy
Connection point (POI)
Primary: Grahamville 161 kV bus ; Alternate: Grahamville – Wickliffe 161 kV line, SIS Primary changed to : Grahamville 161 kV bus
Location
Mccracken County, Kentucky
Technology
Solar: 120 MW
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
LGIA signed, currently suspended
Queue status
Suspended
Entered queue
22 March 2021
Proposed online date
June 2026

Location

Marker shows the centre of Mccracken County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Mccracken County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem