United States › Grid › Interconnection queues › Missouri

HYDRO · MISO

Hydro project J1213, Iron County

Hydro project J1213, Iron County is a 60.0 MW hydro request with a signed interconnection agreement in the MISO interconnection queue, in Iron County, Missouri, connecting to Ameren Missouri.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedJul 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1213
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Taum Sauk 138kV Switchyard, Bus 1 & 2
Location
Iron County, Missouri
Technology
Hydro: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
27 April 2019
Agreement signed
25 July 2023
Proposed online date
November 2024

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Iron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem