SOLAR · ERCOTLampe Solar
Lampe Solar is a 60.2 MW solar request in interconnection study in the ERCOT interconnection queue, in Washington County, Texas.
Queue statusIn planning
- PlanningQueued Aug 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0101
- Grid region
- ERCOT (Texas)
- Developer
- Gransolar Texas Seven LLC
- Connection point (POI)
- Tap 138 kV 7572 Gay Hill - 7573 Lyons
- Location
- Washington County, Texas
- Technology
- Solar: 60.2 MW
- Total requested
- 60.2 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 3 August 2021
- Proposed online date
- December 2027
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem