SOLAR · SOUTHEASTTaylor Creek Two
Taylor Creek Two is a 60.0 MW solar request in interconnection study in the Southeast interconnection queue, in Orange County, Florida, connecting to Orlando Utilities Commission.
Queue statusIn planning
- PlanningQueued Feb 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 202313
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Orlando Utilities Commission
- Connection point (POI)
- Stanton - Indian River 115 kV
- Location
- Orange County, Florida
- Technology
- Solar: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 14 February 2024
- Proposed online date
- December 2026
Location
Marker shows the centre of Orange County; the queue data does not give exact sites.
Other requests in Orange County
- Solar project 343, Orange CountySolar · 74.9 MW · under construction
- Solar project 342, Orange CountySolar · 74.9 MW · under construction
- Solar project 341, Orange CountySolar · 74.9 MW · under construction
- Gas project FC100379, Orange CountyGas · 12.0 MW · in study
- Stanton AGas · 74.7 MW · built
- Orange county Taylor CreekSolar · 74.5 MW · built
- Stanton 1Coal · 30.0 MW · built
- Other project 107, Orange CountyOther · 36.0 MW · withdrawn