United States › Grid › Interconnection queues › Florida
SOLAR · SOUTHEASTSolar project 341, Orange County
Solar project 341, Orange County is a 74.9 MW solar request under construction in the Southeast interconnection queue, in Orange County, Florida, connecting to Duke Energy Florida.
Queue statusUnder construction
- PlanningQueued Jan 2024 (completed)
- Consented (completed)
- Construction (current stage)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 341
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC
- Connection point (POI)
- Sweetwater Switching Station
- Location
- Orange County, Florida
- Technology
- Solar: 74.9 MW
- Total requested
- 74.9 MW
- Service type
- NRIS and ERIS
- Study phase
- Construction
- Queue status
- Active
- Entered queue
- 13 January 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Orange County; the queue data does not give exact sites.
Other requests in Orange County
- Solar project 343, Orange CountySolar · 74.9 MW · under construction
- Solar project 342, Orange CountySolar · 74.9 MW · under construction
- Taylor Creek TwoSolar · 60.0 MW · in study
- Gas project FC100379, Orange CountyGas · 12.0 MW · in study
- Stanton AGas · 74.7 MW · built
- Orange county Taylor CreekSolar · 74.5 MW · built
- Stanton 1Coal · 30.0 MW · built
- Other project 107, Orange CountyOther · 36.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem