Stonewall Solar is a 60.2 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Stonewall County, Texas.
Queue statusIn planning
- PlanningQueued May 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0242
- Grid region
- ERCOT (Texas)
- Developer
- Stonewall PV, LLC
- Connection point (POI)
- #755 BEPC ASPERMONT 69KV
- Location
- Stonewall County, Texas
- Technology
- Solar: 60.2 MW · Battery
- Total requested
- 60.2 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 9 May 2024
- Proposed online date
- January 2029
Location
Marker shows the centre of Stonewall County; the queue data does not give exact sites.