United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTMoccasin Solar
Moccasin Solar is a 604 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Stonewall County, Texas.
Queue statusConsented
- PlanningQueued Sep 2023 (completed)
- ConsentedSep 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0269
- Grid region
- ERCOT (Texas)
- Developer
- Swenson Solar LLC
- Connection point (POI)
- Tapping the 345 kV Line from Kirchhoff (Bus# 60707) to Clear Crossing (Bus# 60515)
- Location
- Stonewall County, Texas
- Technology
- Solar: 604 MW · Battery
- Total requested
- 604 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 7 September 2023
- Agreement signed
- 4 September 2024
- Proposed online date
- July 2027
Location
Marker shows the centre of Stonewall County; the queue data does not give exact sites.
Other requests in Stonewall County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem