United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTPV New Glory
PV New Glory is a 72.5 MW solar request withdrawn in the ERCOT interconnection queue, in Stonewall County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2021 (completed)
- Withdrawn / abandonedMar 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 23INR0377
- Grid region
- ERCOT (Texas)
- Developer
- PREMIER ENGINEERING USA CORP.
- Connection point (POI)
- 6120 Rule 69kV
- Location
- Stonewall County, Texas
- Technology
- Solar: 72.5 MW
- Total requested
- 72.5 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 11 October 2021
- Proposed online date
- September 2024
- Withdrawn
- March 2023
Location
Marker shows the centre of Stonewall County; the queue data does not give exact sites.
Other requests in Stonewall County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem