United States › Grid › Interconnection queues › New York

SOLAR · NYISO

Columbia County 1

Columbia County 1 is a 60.0 MW solar request in interconnection study in the NYISO interconnection queue, in Columbia County, New York, connecting to NYSEG.

Queue statusIn planning
  1. PlanningQueued Jul 2017 (current stage)
  2. ConsentedFeb 2021 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
644
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Hecate Energy Columbia County 1, LLC
Connection point (POI)
Craryville 115kV
Location
Columbia County, New York
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Study phase
FES, SRIS, FS
Queue status
Active
Entered queue
26 July 2017
Agreement signed
8 February 2021
Proposed online date
February 2027

Location

Marker shows the centre of Columbia County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Columbia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem