United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOELP Stuyvesant Solar
ELP Stuyvesant Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Columbia County, New York, connecting to Transco.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2021 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1171
- Grid region
- NYISO (New York)
- Utility / transmission owner
- Transco
- Developer
- ELP Stuyvesant Solar LLC
- Connection point (POI)
- Valkin - Falls Park 115 kV line #19
- Location
- Columbia County, New York
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 14 May 2021
Location
Marker shows the centre of Columbia County; the queue data does not give exact sites.
Other requests in Columbia County
- Kce NY 38Battery storage Β· 250 MW Β· in study
- Columbia County 1Solar Β· 60.0 MW Β· in study
- Kce NY 32Battery storage Β· 250 MW Β· withdrawn
- Kce NY 38Battery storage Β· 250 MW Β· withdrawn
- NY Greenport 85 Middle Rd StorageBattery storage Β· 104 MW Β· withdrawn
- Sketch Book StorageBattery storage Β· 100 MW Β· withdrawn
- Loomis Creek SolarSolar Β· 100 MW Β· withdrawn
- Falls Park Energy StorageBattery storage Β· 100 MW Β· withdrawn
- Loomis Creek ESBattery storage Β· 50.0 MW Β· withdrawn
- NY Hudson Fairview Ave StorageBattery storage Β· 25.2 MW Β· withdrawn
- ELP Chatham StorageBattery storage Β· 20.0 MW Β· withdrawn
- ELP Claverack Solar II LLCSolar + storage Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem