SOLAR + STORAGE · NYISO

ELP Claverack Solar II LLC

ELP Claverack Solar II LLC is a 20.0 MW solar + storage request withdrawn in the NYISO interconnection queue, in Columbia County, New York, connecting to NYTransco/NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedJan 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1264
Grid region
NYISO (New York)
Utility / transmission owner
NYTransco/NM-NG
Developer
ELP Claverack Solar II LLC
Connection point (POI)
Hudson - Churchtown 115kV
Location
Columbia County, New York
Technology
Solar: 20.0 MW · Battery
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
27 September 2021
Withdrawn
January 2022

Location

Marker shows the centre of Columbia County; the queue data does not give exact sites.