Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 92 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AI1-137, Warren County
Solar
155 MWIn study Warren, NJPJM Sep 2022target 2025
Dorsey Road BESS
Battery storage · Horizon Energy Storage Greenfield Project Holdings LLC
155 MWIn study Bexar, TXERCOT Mar 2025target 2029
Berryman Road Storage
Battery storage · Horizon Energy Storage Greenfield Project Holdings LLC
155 MWIn study Archer, TXERCOT Jun 2025target 2029
Onshore wind project J3898, Howard County
Onshore wind
155 MWIn study Howard, IAMISO Feb 2025target 2030
Nuclear project 255, Limestone County
Nuclear
155 MWAgreement signed Limestone, ALSoutheast Aug 2014target 2018
Skycrest Solar Energy Center
Solar
155 MWAgreement signed Jay, INPJM Feb 2019target 2026
Springwater Solar
Solar
155 MWAgreement signed Madison, OHPJM Sep 2019target 2027
Galaxy Storage
Solar + storage · Galaxy Solar, LLC
155 MWIn study Ellis, TXERCOT Mar 2024target 2028
Nuclear project 256, Limestone County
Nuclear
155 MWAgreement signed Limestone, ALSoutheast Aug 2014target 2019
Solar project GEN-2019-045, Woods County
Solar
155 MWAgreement signed Woods, OKSPP May 2019target 2028
Solar + storage project GEN-2024-205, Stafford County
Solar + storage
155 MWIn study Stafford, KSSPP Mar 2025target 2029
Bowstring BESS
Battery storage · Longbow Energy Storage, LLC
155 MWAgreement signed San Patricio, TXERCOT Nov 2020target 2028
Zeta
Solar + storage
155 MWAgreement signed Merced, CACAISO Apr 2020target 2027
Solar + storage project GEN-2021-063, Mccurtain County
Solar + storage
155 MWIn study Mccurtain, OKSPP Apr 2021target 2027
Nuclear project 254, Limestone County
Nuclear
155 MWAgreement signed Limestone, ALSoutheast Aug 2014target 2018
Crystal Flats
Solar + storage
155 MWAgreement signed Kern, CACAISO Apr 2020target 2030
Gunnar BESS
Battery storage · Gunnar Reliability Project LLC
155 MWAgreement signed Hidalgo, TXERCOT Feb 2023target 2026
SunWave Solar
Solar · Buckeye Nueces Bay Solar LLC
154 MWIn study Nueces, TXERCOT May 2023target 2028
Bastion BESS
Battery storage · BESS BASTION LLC
154 MWIn study Matagorda, TXERCOT Jul 2025target 2028
Valcrest BESS
Battery storage · Flexen USA LLC
154 MWIn study Galveston, TXERCOT Dec 2025target 2028
Roble BESS
Battery storage · Flexen USA LLC
154 MWIn study Guadalupe, TXERCOT Aug 2024target 2028
Crowned Heron BESS 2
Battery storage · RWE Renewables
154 MWAgreement signed Fort Bend, TXERCOT Nov 2022target 2026
Cartwheel BESS 1
Battery storage · Cartwheel BESS, LLC
154 MWAgreement signed Hopkins, TXERCOT Jun 2022target 2025
Pavo Creek Storage
Battery storage · Pavo Creek Storage, LLC
154 MWIn study Milam, TXERCOT Feb 2025target 2028
Crowned Heron BESS
Battery storage · RWE Renewables
154 MWAgreement signed Fort Bend, TXERCOT Jul 2022target 2026
Quarter Ranch Solar
Solar · Gransolar Texas Three LLC
154 MWIn study Zapata, TXERCOT Jul 2021target 2028
Badger BESS
Solar + storage · Greasewood BESS, LLC
154 MWIn study Upton, TXERCOT Feb 2025target 2029
Dori BQ BESS
Solar + storage · Sunnyside Energy LLC
154 MWAgreement signed Harris, TXERCOT Feb 2022target 2027
Maderagemela BESS1
Battery storage · Twinwood ES1, LLC
154 MWIn study Waller, TXERCOT Feb 2024target 2027
Pamplona Storage
Solar + storage · Karol Solar V
154 MWIn study Austin, TXERCOT Dec 2024target 2028
Blanco County Behrends Storage
Battery storage · DM-BCB, LLC
154 MWIn study Blanco, TXERCOT Dec 2024target 2028
Bonaparte BESS
Battery storage · Bonaparte BESS, LLC
154 MWIn study Lee, TXERCOT Nov 2023target 2027
Leon BESS
Solar + storage · Leon BESS
154 MWIn study Houston, TXERCOT Nov 2024target 2028
Zinfandel Storage Center
Battery storage
154 MWIn study San Joaquin, CACAISO Apr 2023target 2030
Zorro BESS
Battery storage · ZORRO BESS LLC
154 MWAgreement signed Van Zandt, TXERCOT Mar 2023target 2027
Whiskey BESS
Battery storage · Whiskey BESS LLC
154 MWAgreement signed Van Zandt, TXERCOT Dec 2022target 2027
Wichita County Mawson Storage
Battery storage · DM-WCM, LLC
154 MWIn study Wichita, TXERCOT Dec 2024target 2029
Kit Fox Storage
Battery storage · Kit Fox Storage, LLC
154 MWIn study Henderson, TXERCOT Mar 2023target 2027
Anson BAT
Solar + storage · Anson II Storage LLC
154 MWAgreement signed Jones, TXERCOT Dec 2020target 2027
Grimes Solar
Solar · CG Grimes County LLC
154 MWIn study Grimes, TXERCOT Mar 2022target 2026
Palisade BESS
Battery storage · Flexen USA LLC
154 MWIn study Brazoria, TXERCOT Sep 2025target 2029
Thunder Road Energy Storage
Battery storage · Hecate Grid Thunder Road Storage LLC
153 MWIn study Dallas, TXERCOT Oct 2021target 2027
Dionysus Solar
Solar + storage · Dionysus Solar, LLC
153 MWIn study Houston, TXERCOT Jun 2023target 2027
Bufflehead BESS
Battery storage · Boxcar Energy Storage, LLC
153 MWAgreement signed Collin, TXERCOT Mar 2022target 2027
Cairos Solar
Solar + storage · Cairos Solar, LLC
153 MWIn study Kinney, TXERCOT Oct 2023target 2026
Eighteenmile Solar SLF
Solar + storage · Weser Solar, LLC
153 MWIn study Goliad, TXERCOT Aug 2021target 2026
Senator Aggreko Storage
Solar + storage · Senator Aggreko Storage LLC
153 MWIn study Maverick, TXERCOT Nov 2023target 2026
Nuclear project J3815, St. Charles Parish County
Nuclear
153 MWIn study St. Charles Parish, LAMISO Jun 2024target 2026
Silver Dollar Storage
Solar + storage · Silver Dollar Solar Project, LLC
153 MWIn study Freestone, TXERCOT Jun 2024target 2028
Pradera Storage
Solar + storage · Pradera Storage, LLC
153 MWIn study Webb, TXERCOT Jan 2021target 2027
Page 92 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)