United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Bonaparte BESS

Bonaparte BESS is a 154 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Lee County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0283
Grid region
ERCOT (Texas)
Developer
Bonaparte BESS, LLC
Connection point (POI)
7568 Lincoln 138 kV
Location
Lee County, Texas
Technology
Battery: 154 MW
Total requested
154 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
14 November 2023
Proposed online date
December 2027

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Lee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem