United States › Grid › Interconnection queues › Oklahoma
SOLAR + STORAGE · SPPSolar + storage project GEN-2021-063, Mccurtain County
Solar + storage project GEN-2021-063, Mccurtain County is a 155 MW solar + storage request in interconnection study in the SPP interconnection queue, in Mccurtain County, Oklahoma, connecting to AEP.
- PlanningQueued Apr 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2021-063
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Craig JCT 138kV
- Location
- Mccurtain County, Oklahoma
- Technology
- Solar: 155 MW · Battery
- Total requested
- 155 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 28 April 2021
- Proposed online date
- December 2027
Location
Marker shows the centre of Mccurtain County; the queue data does not give exact sites.
Other requests in Mccurtain County
- Solar + storage project GEN-2020-020, Mccurtain CountySolar + storage · 202 MW · agreement signed
- Gas project GEN-2000-004, Mccurtain CountyGas · 800 MW · withdrawn
- Gas project GEN-2000-009, Mccurtain CountyGas · 500 MW · withdrawn
- Battery storage project GEN-2022-091, Mccurtain CountyBattery storage · 150 MW · withdrawn
- Solar project GEN-2022-090, Mccurtain CountySolar · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem