Solar + storage project GEN-2021-063, Mccurtain County

Solar + storage project GEN-2021-063, Mccurtain County is a 155 MW solar + storage request in interconnection study in the SPP interconnection queue, in Mccurtain County, Oklahoma, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2021-063
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Craig JCT 138kV
Location
Mccurtain County, Oklahoma
Technology
Solar: 155 MW · Battery
Total requested
155 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
28 April 2021
Proposed online date
December 2027

Location

Marker shows the centre of Mccurtain County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Mccurtain County