πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

SOLAR Β· SPP

Solar project GEN-2022-090, Mccurtain County

Solar project GEN-2022-090, Mccurtain County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Mccurtain County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-090
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Valiant Substation 138kV
Location
Mccurtain County, Oklahoma
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
15 November 2022
Proposed online date
September 2026
Withdrawn
March 2025

Location

Marker shows the centre of Mccurtain County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Mccurtain County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem