SOLAR + STORAGE · SPPSolar + storage project GEN-2024-205, Stafford County
Solar + storage project GEN-2024-205, Stafford County is a 155 MW solar + storage request in interconnection study in the SPP interconnection queue, in Stafford County, Kansas, connecting to SUNC.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-205
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- St. John 115 kV Substation
- Location
- Stafford County, Kansas
- Technology
- Solar: 155 MW · Battery
- Total requested
- 155 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- October 2029
Location
Marker shows the centre of Stafford County; the queue data does not give exact sites.
Other requests in Stafford County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem