Solar + storage project GEN-2024-007, Stafford County

Solar + storage project GEN-2024-007, Stafford County is a 80.0 MW solar + storage request in interconnection study in the SPP interconnection queue, in Stafford County, Kansas, connecting to MIDW.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-007
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
MIDW
Connection point (POI)
Seward 115 kV Substation
Location
Stafford County, Kansas
Technology
Solar: 80.0 MW · Battery
Total requested
80.0 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
30 April 2024
Proposed online date
December 2028

Location

Marker shows the centre of Stafford County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Stafford County