Cartwheel BESS 1

Cartwheel BESS 1 is a 154 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Hopkins County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2022 (completed)
  2. ConsentedNov 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0494
Grid region
ERCOT (Texas)
Developer
Cartwheel BESS, LLC
Connection point (POI)
Tap 345kV 1697 Sulphur Springs Switch – 2464 Cash Switch
Location
Hopkins County, Texas
Technology
Battery: 154 MW
Total requested
154 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
2 June 2022
Agreement signed
10 November 2023
Proposed online date
December 2025

Location

Marker shows the centre of Hopkins County; the queue data does not give exact sites.