🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Juniperusss

Juniperusss is a 80.3 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Hopkins County, Texas.

Queue statusIn planning
  1. PlanningQueued Jan 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0304
Grid region
ERCOT (Texas)
Developer
BLUE STONE RENEWABLE XXI LLC
Connection point (POI)
TAP CASHSW_T5 (2464) -SULSP_SS1_5 (1697)
Location
Hopkins County, Texas
Technology
Solar: 80.3 MW · Battery
Total requested
80.3 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
11 January 2024
Proposed online date
July 2029

Location

Marker shows the centre of Hopkins County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hopkins County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem