SOLAR · ERCOT

Blarney Solar

Blarney Solar is a 81.0 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Hopkins County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2022 (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0326
Grid region
ERCOT (Texas)
Developer
Blarney Solar Project LLC
Connection point (POI)
tap 138kV 1815 Cumby Tap - 1819 Commerce South Sub
Location
Hopkins County, Texas
Technology
Solar: 81.0 MW
Total requested
81.0 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
5 July 2022
Agreement signed
22 April 2024
Proposed online date
July 2027

Location

Marker shows the centre of Hopkins County; the queue data does not give exact sites.