SOLAR · ERCOT

CH Solterra LLC

CH Solterra LLC is a 143 MW solar request in interconnection study in the ERCOT interconnection queue, in Hopkins County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0229
Grid region
ERCOT (Texas)
Developer
CH Solterra LLC
Connection point (POI)
Tap 138kV 11796 White Oak POI - 11797 Brinker POI
Location
Hopkins County, Texas
Technology
Solar: 143 MW
Total requested
143 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 March 2021
Proposed online date
December 2026

Location

Marker shows the centre of Hopkins County; the queue data does not give exact sites.