United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTJuniperus BESS
Juniperus BESS is a 170 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Hopkins County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0097
- Grid region
- ERCOT (Texas)
- Developer
- BLUE STONE RENEWABLE XXI LLC
- Connection point (POI)
- TAP CASHSW_T5 (2464) -SULSP_SS1_5 (1697)
- Location
- Hopkins County, Texas
- Technology
- Battery: 170 MW · Battery
- Total requested
- 170 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 30 October 2023
- Proposed online date
- July 2029
Location
Marker shows the centre of Hopkins County; the queue data does not give exact sites.
Other requests in Hopkins County
- Pine Forest SolarSolar · 302 MW · agreement signed
- Pine Forest BESSBattery storage · 201 MW · agreement signed
- Cartwheel BESS 1Battery storage · 154 MW · agreement signed
- Claxton SolarSolar · 151 MW · agreement signed
- Lucky 7 SolarSolar · 102 MW · agreement signed
- Blarney SolarSolar · 81.0 MW · agreement signed
- Dairyland StorageBattery storage · 302 MW · in study
- Palomino SolarSolar + storage · 301 MW · in study
- Cartwheel BESS 2Battery storage · 157 MW · in study
- Palomino StorageSolar + storage · 153 MW · in study
- CH Solterra LLCSolar · 143 MW · in study
- JuniperusssSolar + storage · 80.3 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem