Badger BESS

Badger BESS is a 154 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Upton County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0213
Grid region
ERCOT (Texas)
Developer
Greasewood BESS, LLC
Connection point (POI)
345 kV North McCamey (Bus# 76000)
Location
Upton County, Texas
Technology
Battery: 154 MW · Battery
Total requested
154 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
12 February 2025
Proposed online date
May 2029

Location

Marker shows the centre of Upton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Upton County