BATTERY STORAGE · ERCOT

Thunder Road Energy Storage

Thunder Road Energy Storage is a 153 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Dallas County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0391
Grid region
ERCOT (Texas)
Developer
Hecate Grid Thunder Road Storage LLC
Connection point (POI)
12491 FISH CREEK 138KV
Location
Dallas County, Texas
Technology
Battery: 153 MW
Total requested
153 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 October 2021
Proposed online date
May 2027

Location

Marker shows the centre of Dallas County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Dallas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem