🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

OTHER · ERCOT

Atlanta TxHSR TPSS DS-1

Atlanta TxHSR TPSS DS-1 is a 50.0 MW other request in interconnection study in the ERCOT interconnection queue, in Dallas County, Texas.

Queue statusIn planning
  1. PlanningQueued Jan 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0006
Grid region
ERCOT (Texas)
Developer
Texas Central Rail Holdings, LLC
Connection point (POI)
tap 138kV 2429 Watermill E - 3083 Wilmer
Location
Dallas County, Texas
Technology
Other: 50.0 MW
Total requested
50.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
30 January 2019
Proposed online date
July 2028

Location

Marker shows the centre of Dallas County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Dallas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem