🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Empire Central BESS

Empire Central BESS is a 10.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Dallas County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2024 (completed)
  2. ConsentedMay 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0659
Grid region
ERCOT (Texas)
Developer
SMT Dallas III LLC
Connection point (POI)
Station name: EMPCT, Load name: LDLXFMR2, XFMR Number: 2, Bus Number:2799, Voltage: 138kV
Location
Dallas County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
29 January 2024
Agreement signed
20 May 2024
Proposed online date
December 2025

Location

Marker shows the centre of Dallas County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Dallas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem