BATTERY STORAGE · ERCOT

Blanco County Behrends Storage

Blanco County Behrends Storage is a 154 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Blanco County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0616
Grid region
ERCOT (Texas)
Developer
DM-BCB, LLC
Connection point (POI)
#70482 Blanco Substation 138 kV - currently being upgraded
Location
Blanco County, Texas
Technology
Battery: 154 MW
Total requested
154 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 December 2024
Proposed online date
December 2028

Location

Marker shows the centre of Blanco County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem