🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Dorsey Road BESS

Dorsey Road BESS is a 155 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Bexar County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0342
Grid region
ERCOT (Texas)
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Connection point (POI)
Tap 138 kV Chavanea (5085) - Palo Alto (5330).
Location
Bexar County, Texas
Technology
Battery: 155 MW
Total requested
155 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
6 March 2025
Proposed online date
August 2029

Location

Marker shows the centre of Bexar County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bexar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem