Ferdinand Grid BESS

Ferdinand Grid BESS is a 206 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bexar County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2021 (completed)
  2. ConsentedNov 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0422
Grid region
ERCOT (Texas)
Developer
Ferdinand Grid, LLC
Connection point (POI)
5260 Leon Creek 138kV
Location
Bexar County, Texas
Technology
Battery: 206 MW
Total requested
206 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
1 March 2021
Agreement signed
28 November 2022
Proposed online date
May 2026

Location

Marker shows the centre of Bexar County; the queue data does not give exact sites.