United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Bexar ESS

Bexar ESS is a 103 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bexar County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2021 (completed)
  2. ConsentedJul 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0381
Grid region
ERCOT (Texas)
Developer
Bexar ESS LLC
Connection point (POI)
5007 Alamo One 138kV
Location
Bexar County, Texas
Technology
Battery: 103 MW
Total requested
103 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
21 September 2021
Agreement signed
31 July 2023
Proposed online date
December 2025

Location

Marker shows the centre of Bexar County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bexar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem