Taormina Storage

Taormina Storage is a 232 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bexar County, Texas.

Queue statusConsented
  1. PlanningQueued Apr 2022 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0479
Grid region
ERCOT (Texas)
Developer
Taormina Storage Project LLC
Connection point (POI)
Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465)
Location
Bexar County, Texas
Technology
Battery: 232 MW
Total requested
232 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
18 April 2022
Agreement signed
14 April 2025
Proposed online date
May 2029

Location

Marker shows the centre of Bexar County; the queue data does not give exact sites.