United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTTaormina Storage
Taormina Storage is a 232 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Bexar County, Texas.
Queue statusConsented
- PlanningQueued Apr 2022 (completed)
- ConsentedApr 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget May 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0479
- Grid region
- ERCOT (Texas)
- Developer
- Taormina Storage Project LLC
- Connection point (POI)
- Tap 138kV VH Braunig (5025) to Valley Road 138kV (5465)
- Location
- Bexar County, Texas
- Technology
- Battery: 232 MW
- Total requested
- 232 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 18 April 2022
- Agreement signed
- 14 April 2025
- Proposed online date
- May 2029
Location
Marker shows the centre of Bexar County; the queue data does not give exact sites.
Other requests in Bexar County
- Lavender Storage ProjectBattery storage · 232 MW · agreement signed
- Ferdinand Grid BESSBattery storage · 206 MW · agreement signed
- Padua Grid BESS Unit 3Battery storage · 201 MW · agreement signed
- El Patrimonio SolarSolar · 152 MW · agreement signed
- Padua Grid BESS Unit 2Battery storage · 151 MW · agreement signed
- Alamo City BESSBattery storage · 128 MW · agreement signed
- Louisa Energy StorageBattery storage · 103 MW · agreement signed
- Bexar ESSBattery storage · 103 MW · agreement signed
- Beck_Road BESS1Battery storage · 10.0 MW · agreement signed
- Howard Road BESSBattery storage · 618 MW · in study
- Orbit Energy StorageBattery storage · 502 MW · in study
- Bernice Energy StorageBattery storage · 403 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem