United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA — page 29
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project GEN-2024-045, Hansford County Solar |
345 MW | In study |
| Solar + storage project 8, Sacramento County Solar + storage |
344 MW | In study |
| Solar project J4000, Scott County Solar |
343 MW | In study |
| Rabbit Hollow Energy Storage Battery storage · Rabbit Hollow Energy Storage, LLC |
342 MW | In study |
| Gas project J1839, Macon County Gas |
340 MW | In study |
| Solar + storage project T2-052, Emery County Solar + storage |
340 MW | In study |
| Baird North Wind Onshore wind · BMP Wind, LLC |
340 MW | Agreement signed |
| Other project Q553, Navajo County Other |
340 MW | In study |
| Solar project J3950, Clark County Solar |
340 MW | In study |
| Solar + storage project Company JX, Pershing County Solar + storage |
340 MW | Paused / redesign |
| Onshore wind project J3991, Mclean County Onshore wind |
340 MW | In study |
| Solar + storage project J4088, Lee County Solar + storage |
340 MW | In study |
| Alle Catt II Wind Onshore wind · Alle-Catt Wind Energy LLC |
339 MW | In study |
| Titus Low Carbon Ventures Solar 1 Solar · Vaquero Solar, LLC |
338 MW | In study |
| Gas project 20240829009, Colleton County Gas · DESC - Generation |
338 MW | In study |
| Gas project 20240829010, Colleton County Gas · DESC - Generation |
338 MW | In study |
| Gas project 20240829011, Colleton County Gas · DESC - Generation |
338 MW | In study |
| Solar project J3943, Vigo County Solar |
337 MW | In study |
| Solar project IC-1071, Perry County Solar |
336 MW | Agreement signed |
| Briggs Storage Solar + storage · IP Quantum III, LLC |
336 MW | Agreement signed |
| Greyhound Solar Solar · Rockhound Solar 2, LLC dba "Greyhound Solar" |
336 MW | Agreement signed |
| Cielo Vista Power Gas Plant Gas · Cielo Vista Power, LLC |
335 MW | In study |
| River Boat Power Gas Plant Gas · Champion Creek Power, LLC |
334 MW | In study |
| Dandelion Hybrid Solar Solar + storage |
334 MW | In study |
| Three Canes Solar SLF Solar · Three Canes Solar LLC |
333 MW | Agreement signed |
| Mountaineer Solar Solar · Mustang Mountaineer Solar LLC |
332 MW | In study |
| Gas project Q76, Pinal County Gas |
332 MW | In study |
| Harquahala Sunrise 2 Solar + storage |
330 MW | In study |
| Battery storage project J4168, Goodhue County Battery storage |
330 MW | In study |
| Wind + storage project GI-CS-2025-04, Laramie County Wind + storage |
330 MW | In study |
| Solar + storage project T2-051, Carbon County Solar + storage |
330 MW | In study |
| Other project 590, Elmore County Other · Appaloosa Wind And Solar LLC |
330 MW | Agreement signed |
| Battery storage project 696, Owyhee County Battery storage · KCE ID 1, LLC |
330 MW | Agreement signed |
| Solar project GEN-2023-015, Finney County Solar |
330 MW | In study |
| Battery storage project 792, Elmore County Battery storage |
330 MW | In study |
| Replace 330 MW of CLECO.DPS Unit with solar; Dolet Hills Other |
330 MW | In study |
| Other project Q615, Maricopa County Other |
330 MW | In study |
| Other project Q596, Yuma County Other |
330 MW | In study |
| Battery storage project AJ1-011, Lake County Battery storage |
328 MW | In study |
| Ariella Solar Solar + storage |
327 MW | Agreement signed |
| Onshore wind project 408, Wheatland County Onshore wind |
326 MW | In study |
| Onshore wind project C013, Meagher County Onshore wind |
326 MW | In study |
| Stargazer II Solar + storage · RWE Solar Development, LLC |
325 MW | In study |
| Solar + storage project 655, Bear Lake County Solar + storage · Aurora Solar LLC |
325 MW | Paused / redesign |
| Other project 771, Baker County Other |
325 MW | In study |
| Solar + storage project GI-2025-03, Kiowa County Solar + storage |
325 MW | In study |
| Battery storage project 25-IC-1375, Jackson County Battery storage |
325 MW | In study |
| Solar + storage project G0817, Yakima County Solar + storage |
325 MW | In study |
| Stargazer I Solar + storage · RWE Solar Development, LLC |
325 MW | In study |
| Solar project J1598, Calcasieu Parish County Solar |
325 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)