Other project 771, Baker County

Other project 771, Baker County is a 325 MW other request in interconnection study in the West interconnection queue, in Baker County, Oregon, connecting to Idaho Power Company.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
771
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
North Powder 230kV Substation
Location
Baker County, Oregon
Technology
Solar: 325 MW · Wind · Battery
Total requested
325 MW
Service type
NRIS and ERIS
Study phase
Facility Study
Queue status
Active
Entered queue
14 April 2025
Proposed online date
December 2029

Location

Marker shows the centre of Baker County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Baker County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem